Completed Projects

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option

Recently completed projects

Project Status Timeframe Summary
US-34 Centerra 16” Waterline  Completed  September-October 2025 This project connects and “loops” new waterline along the Schmer and McWhinney properties off Eisenhower with our existing system, allowing water to flow through multiple paths when needed and improving both water quality and system reliability for our customers. 
Annual Hydrant Flushing  Completed April-May 2025   Crews started in mid-April on the west side of the city and moved east until complete. Here's more info about the project, which included an interactive map so customers could see when hydrant flushing would reach their neighborhood. 
Citywide Advanced Meter Infrastructure (AMI) Deployment Completed  February 2024-April 2025  Our city-wide deployment exchanged existing electric meters for advanced meters. Here's more info about the project. 
Water utility improvements on North Taft Avenue Completed   July 2024-Fall 2024 Replacing aging water infrastructure beneath North Taft Avenue from 10th Street to 29th Street. Here's more info about the project.
2024 Water Service Line Potholing Completed September-October 2024 Using contracted teams from AGL Construction to inspect and catalog water service line material using potholing methods. Here's more info about the project. 
Sweetheart Alley Sanitary Sewer Replacement Completed July 2023 - December 2023 The sanitary sewer line beneath Sweetheart Alley was originally installed in the 1920s. The line reached the end of its useful life and was replaced. Here's more info about the project.
2023 Customer Survey Completed March-April 2023 A holistic customer survey was sent to Water and Power customers to give comprehensive feedback on our performance and goals for the future. Here's more info about the project.

Older projects

Loveland's Wastewater Treatment Plant is now known as the Loveland Water Reclamation Facility. Learn more about the completed expansion project below. 

Project Overview

The Wastewater Treatment Plant Biological Nutrient Removal (BNR) and Digester Improvements project evolved through the need to meet three main objectives:

  • Meeting regulatory requirements for the reduction of nitrogen and phosphorus released to the Big Thompson River.
  • Increasing capacity to meet population growth. The plant will be re-rated from 10 million gallons per day (MGD) to 12 MGD allowing for an additional 15 to 20 years of growth.
  • Replacement of aging infrastructure.
The project utilized the Collaborative Project Delivery model referred to in the industry as Construction Manager-at-Risk (CMAR).

Construction Facts

  • Over 2,000,000 working hours
  • 887 working days
  • Zero recordable loss-time injuries
  • 5,900 cubic yards of concrete placed
  • 706 million gallons of sewage successfully bypass pumped
  • Zero discharge violations during construction

Project Cost and Timeline 

  • Project Design June 2015 - April 2017
  • Project Construction April 2017 - October 2019
  • Total Project Cost $41,020,000